Tool · Engineering design

Electrical load list tool for early plant design

List your motors and loads, set a diversity factor and spare capacity, and get an early estimate of connected load, running load and maximum demand in kVA and amps. Made for project engineers sizing up a new plant or an upgrade.

Preliminary estimate for early planning only. This is not a design. Maximum demand for a supply application, and for sizing mains, switchboards and transformers, must be assessed to AS/NZS 3000 by a qualified person.

Optional. Used on the CSV and the printout.
Change to 400 if your project uses it.
The share of the running load you expect at the same time. 1 means all duty loads run together.
Allowance for future loads.
The power factor the supply sees for loads on a VSD. Check the drive data sheet.
Drive losses, added to the motor losses for loads on a VSD.
Electrical load list. One row for each motor or load.
TagDescriptionRated kWQtyDutyStarterLoad factor %Power factorEfficiency %Running kWEst. amps eachRemove
Connected load0.0 kW

0.0 kVA. Every load listed, 0 in total, including 0 on standby. Nameplate total 0.0 kW.

Estimated running load0.0 kW

0.0 kVA, 0 A. Duty loads at their load factor.

Estimated maximum demand0.0 kVA

0 A at 415 V three-phase. 0.0 kW at power factor 0.00. Diversity factor 1.00.

With spare capacity0.0 kVA

0 A. Maximum demand plus 20% spare.

Starters and feeders by type
Starter typeCountRated kW
DOL00.0
Soft starter00.0
VSD00.0
Feeder (non-motor)00.0
Largest single loadNone yet

Copy the summary and paste it into the contact form, or email the CSV to [email protected]. We will come back with a budget price for the switchboards, motor control and automation. Your list is saved in this browser only, so it is still here when you come back.

How the numbers are worked out

Each row is turned into electrical input power, then the rows are added up as kW and kVAr so the kVA total allows for different power factors.

  • Input kW for each unitrated kW ÷ efficiency. On a VSD, efficiency = motor efficiency × VSD efficiency
  • Connected load (kW)sum of quantity × input kW, for every row including standby
  • Running load (kW)sum of quantity × input kW × load factor, for duty rows only. Standby rows count as zero
  • kVAr for each rowkW × tan(arccos(power factor)). On a VSD the supply sees the drive, so the VSD line-side power factor is used
  • kVA√(total kW² + total kVAr²)
  • Estimated maximum demandrunning load × diversity factor
  • AmpskVA × 1000 ÷ (√3 × supply voltage)
  • With spare capacitymaximum demand × (1 + spare capacity %)
  • Est. amps eachinput kW ÷ power factor × 1000 ÷ (√3 × supply voltage)

What each input means

  • Rated kW: the motor nameplate power. For heaters and other non-motor loads, enter the electrical kW, choose Feeder and set efficiency to 100
  • Duty or standby: standby units count towards connected load but not running load
  • Starter: DOL, soft starter or VSD. It feeds the starter count, and for a VSD it changes the power factor and adds drive losses
  • Load factor: how hard the load works when it runs, as a percentage of its rating
  • Power factor and efficiency: take these from the motor data sheet. The starting values are placeholders only
  • Diversity factor: the share of the running load you expect at the same time
  • Spare capacity: an allowance for loads added later

What this tool does not do

  • Motor starting currents and voltage dip
  • Harmonics from VSDs
  • Cable sizing, voltage drop, protection, discrimination and fault levels
  • Single-phase loads and phase balance
  • Power factor correction
  • The maximum demand methods in AS/NZS 3000, or your network distributor's rules

Motor power factor and efficiency also fall at part load, which this estimate ignores. An electrical designer deals with all of these in the design.

From load list to budget price

A load list is one of the first things an electrical team asks for on a new plant or an upgrade. With it we can draft the single-line diagram, work out the switchboards and motor control the plant needs, and give you a budget price early enough to shape the project. AMC then designs, builds, installs and commissions the package with one team.

FAQs

Common questions about load lists

What is an electrical load list?

A table of every motor and electrical load in a plant, with its rating, how it is started and how hard it works. Early in a project it is used to estimate the size of the supply, the switchboards and the motor control centre.

What is the difference between connected load, running load and maximum demand?

Connected load is everything installed, added together. Running load is what the duty equipment draws at its normal loading. Maximum demand is the highest load the supply is expected to see, allowing for the fact that not everything runs at once.

What diversity factor should I use?

It depends on the process. A plant where every drive runs hard all shift is close to 1. A plant with batch steps, cycling loads or seasonal sections is lower. If you don't know, leave it at 1 for a conservative first estimate and let your electrical designer refine it.

How do I convert kW to amps at 415 V three-phase?

Amps = kW × 1000 ÷ (√3 × 415 × power factor × efficiency). For example, a 15 kW motor at 0.85 power factor and 90% efficiency draws about 27 A at full load.

Can I use this for a supply application or to size a transformer?

No. It is an early planning estimate. Maximum demand for a supply application must be assessed to AS/NZS 3000 by a qualified person, and your network distributor has its own requirements.

Why does the tool use 415 V?

Many Australian load lists still use 415 V for three-phase calculations. The nominal supply voltage is 230/400 V (AS 60038). Change the voltage in the settings if your project uses 400 V.

Is my load list saved or sent anywhere?

It is saved in your browser on this device only, so it is still there when you come back. Nothing is sent to AMC unless you send it.

Next step

Got a plant, machine or board that needs sorting?

Send us the scope, drawings or a few photos. An engineer reads every request and comes back within one business day with next steps and a clear, upfront price.

Project engineer or OEM? Send a P&ID, equipment list or scope for a budget price.

Call nowEmailGet a quote