The electrical and automation scope for a new process plant: a guide for project engineers

What the package includes, the deliverables in the order they are produced, the gaps that cause cost blow-outs, and what an integrator needs from you to price it properly.

On a new process plant the electrical and automation package is often a smaller line in the budget than the process equipment, and one of the easiest to get wrong. It is often scoped late, from an equipment list that is still moving, by people whose main job is the process. This guide is written for process, mechanical and project engineers who have to scope, budget or buy that package.

What the electrical and automation package includes

Names differ between projects (electrical and instrumentation, E&I, EIC, electrical and controls), but a complete package for a process plant normally covers these parts.

  • Power supply: the connection to the electricity network, any transformer, metering and the consumer mains
  • Distribution: main switchboard, distribution boards and power factor correction where needed
  • Motor control: motor control centres (MCCs) with starters, soft starters and variable speed drives
  • Field electrical: cable tray, power and control cabling, local isolators, junction boxes and terminations
  • Instrumentation: supply, installation and calibration of instruments, and the cabling back to the control system
  • Control system: PLC and I/O panels, operator screens (HMI), SCADA, data logging and reporting
  • Networks: the control network, links to vendor packages and secure remote access
  • Safety: emergency stops, guard interlocks and other safety functions, and hazardous area equipment where it applies
  • Building services for the plant: lighting, general power, earthing and the switchroom fit-out
  • Engineering and documents: design, drawings, software, test records, as-built drawings and manuals
  • Site work: installation, inspection and testing, commissioning and operator training

Before you compare prices, check which of these each price includes. Two quotes for "the electrical" can differ by whole items on this list.

The deliverables, in order

Each document feeds the next, so the order matters. Skipping ahead, for example pricing an MCC before the load list has settled, is where rework starts.

  1. Process information. Process description, P&ID or process flow diagram and the equipment list. These come from the process and mechanical team and everything else is built on them.
  2. Electrical load list. Every motor, heater and other load with its rating, duty and starting method. It gives the maximum demand. You can rough one out with our electrical load list tool.
  3. Supply assessment and connection application. Is the existing supply big enough? If not, what does the electricity distributor need to provide?
  4. Single line diagram. One drawing showing the supply, transformer, switchboards, MCCs and major loads, with ratings and fault levels.
  5. Motor and starter schedule, MCC and switchboard design. The starting method for each motor, then the layout, ratings and form of the assemblies.
  6. Instrument list and I/O list. Every instrument, valve and signal, and which PLC input or output it lands on.
  7. Functional description. How the plant is to run, written in plain words: sequences, interlocks, alarms, setpoints and operator modes. Some projects call it a control philosophy or functional design specification.
  8. Network architecture. How PLCs, drives, HMIs, SCADA and vendor packages connect, and how remote access works.
  9. Hazardous area classification where flammable or combustible materials are present, and the safety risk assessment that defines the safety functions.
  10. Cable schedule, routes and layouts. Cable sizes and lengths, tray routes, switchroom and field equipment locations.
  11. Schematics and panel drawings. The detailed drawings the boards and panels are built from.
  12. Software and factory test. PLC, HMI and SCADA software written to the functional description, then tested with the panels before they leave the workshop.
  13. Installation, inspection and testing. Site work to the drawings, with test records.
  14. Commissioning. I/O checks, then functional testing of each sequence, first dry and then with product.
  15. Handover. As-built drawings, software backups, manuals and operator training.

Six gaps that cause cost blow-outs

These are the items most often missing from an early scope. None is exotic. Each one is cheap to settle on paper and expensive to discover on site.

1. Supply capacity and the network connection

The plant's maximum demand decides whether the existing supply is enough or whether you need a larger connection, a new transformer or work on the network. A new or larger connection needs an application to the local electricity distributor, and its design, approval and construction steps run to the distributor's timetable, not the project's. It is often the longest lead item on the electrical side.

What to do: get a load list together early, even a rough one, and start the conversation with the distributor as soon as you have a sensible maximum demand. Ask what you will be charged for, and whether large motors or drives will need extra studies. Rules differ between states and between distributors.

2. Motor starting method

How each motor starts (direct on line, star-delta, soft starter or variable speed drive) changes the size and cost of the MCC, the cable, the heat in the switchroom and the effect on the supply. A large motor started direct on line can dip the voltage for everything else on the site. Drives add harmonics and may need filters and screened cable.

What to do: ask the process engineer which motors really need speed control, and settle the starting method for every motor of any size before the MCC is priced.

3. Hazardous areas

If the plant handles flammable liquids, gases or combustible dusts, parts of it may need to be classified as hazardous areas under AS/NZS 60079. Electrical equipment in those zones has to be certified for the zone, installed with suitable wiring methods, inspected and recorded in a verification dossier. Certified equipment costs more and can take longer to get.

What to do: have the areas classified before instruments, motors and lights are selected. Finding out after the equipment is bought is the expensive way. Our hazardous area guide explains the basics.

4. Safety functions

Emergency stops, guard interlocks, light curtains and safe shutdown sequences come out of a risk assessment, done to AS 4024 for machinery. Each safety function needs the right hardware and has to be tested and validated. Left late, they turn up as extra I/O, a safety controller that was never in the panel design, and rework on guarding.

What to do: run the risk assessment during design, with the mechanical designer involved, and include the safety hardware in the panel and I/O design from the start. See our AS 4024 guide.

5. Network and remote access

A modern plant has PLCs, drives, operator screens, SCADA and vendor packages all on a network. Someone has to decide the architecture, who supplies the switches and fibre, how the plant network is kept apart from the office network, what data the business wants out of the plant, and how the integrator and equipment vendors will reach it securely for support.

What to do: agree the network architecture and remote access at design stage. For every vendor package with its own controller, agree the interface and signal list before the vendor's order is placed.

6. Spare capacity

Plants grow. A little spare is cheap at design stage; adding a section to a full MCC, or finding room in a full switchroom, is not.

What to do: agree a spare allowance up front for the supply and transformer, main switchboard, MCC ways, PLC I/O, cable tray and switchroom floor space. If a second stage or a second line is likely, say so, and it can be allowed for.

Smaller items that also get missed

  • The switchroom itself: the building, its air conditioning and who supplies them
  • Cable route lengths, trenching and road crossings on a spread-out site
  • Lighting, general power and earthing for the plant area
  • Who supplies, installs and calibrates the instruments
  • Standby power, and what has to keep running in an outage
  • Commissioning time with product, operator training and as-built drawings

Need help with this at your plant? Send us the scope, drawings or a few photos and an engineer will reply within one business day.

What to give an integrator for an accurate price

A price is only as good as the information behind it. You do not need all of this for a budget figure, but each item you can add narrows the range and removes an assumption.

  • Process description, and a P&ID or process flow diagram, even in draft
  • Equipment list with motor ratings in kW and which motors need speed control
  • Vendor packages that arrive with their own control panel, and what each vendor supplies
  • Site layout with rough distances between the supply, switchroom and plant
  • What is known about the existing supply, or that a new connection is needed
  • Any flammable liquids, gases or combustible dusts on site
  • How automated the plant should be and how many operators will run it
  • Reporting and data the business wants from the plant
  • Preferred PLC, drive and SCADA brands, and any client specifications
  • Who installs: the integrator, your contractor or the site's electricians
  • Site conditions: greenfield or inside an operating plant, and how remote it is
  • Spare capacity and future stages to allow for
  • Key dates, and whether you need a budget figure or a firm price

Where an item is not known yet, a good integrator states the assumption in the price instead of leaving it out. Read the assumptions and exclusions as carefully as the number.

How staging works

You do not have to buy the whole package in one order. Most projects are better split into stages, each with its own scope and price, so the commitment grows as the design firms up.

  1. Concept and budget price. A first load list, a scope and a budget price with assumptions, for the feasibility study or funding case.
  2. Front-end design. Load list, single line diagram, I/O list and functional description. Enough to fix the scope, start the connection application and firm up the price.
  3. Detailed design. MCC and switchboard design, schematics, cable schedule, network architecture, safety and hazardous area design.
  4. Build and factory test. Boards and panels built, software written and the two tested together before delivery.
  5. Installation and commissioning. Site work, testing, commissioning with product, training and handover.
  6. Support. Remote and on-site support, changes, and as-built documents kept current.

If you plan to build the plant more than once, say so at the start. A design set up to be reused makes the second plant simpler than the first.

How AMC helps

AMC Electrical & Automation works with project teams as their electrical and automation engineers: budget price, design, switchboards and MCCs built in our Griffith workshop, PLC and SCADA software, then installation and commissioning by our own crew, Australia-wide. We are happy to sign an NDA before you send us anything.

This guide is general information only. Requirements vary with the site, the state and the electricity distributor, so get project-specific advice before you commit to a design.

FAQs

Common questions about new plant electrical scope

What is included in the electrical scope of a new process plant?

Normally the power supply and network connection, main switchboard and motor control centres, field cabling and instruments, the PLC, HMI and SCADA control system, networks, safety functions and any hazardous area equipment, plus the design documents, installation, testing and commissioning.

What is an electrical load list and why does it come first?

It is a list of every motor, heater and other electrical load with its rating, duty and starting method. It gives the plant's maximum demand, which sizes the supply, transformer, switchboards and cables. Until it exists, nothing else can be sized properly.

What is a single line diagram?

A single drawing that shows the supply, transformer, switchboards, MCCs and major loads as one line, with their ratings. It is the map of the plant's power system and the first drawing a distributor or switchboard builder will ask for.

What is a functional description?

A plain-language document that says how the plant is to run: start and stop sequences, interlocks, alarms, setpoints and operator modes. The PLC and SCADA software is written to it and tested against it. It is also called a control philosophy or functional design specification.

When should the electrical and automation engineer get involved?

At concept stage. Supply capacity, motor starting, hazardous areas and safety functions all affect the layout and the budget, and they are far cheaper to settle on paper than on site.

How accurate is a budget price for the electrical package?

It depends on the information behind it. An early budget price is built on a first load list and stated assumptions. It firms up after front-end design, when the load list, single line diagram, I/O list and functional description are done.

Who applies for the network connection?

Usually the site owner, or their electrical engineer or contractor on their behalf, applies to the local electricity distributor. The process and the charges differ between states and distributors, so check with yours early.

Next step

Have a plant, machine or process to deliver?

Send us the process description, P&ID or equipment list, or call and talk it through with an engineer. If you want an NDA in place first, say so and we will sign it before you send anything.

Project engineer or OEM? Send a P&ID, equipment list or scope for a budget price.

Call nowEmailGet a quote